Back down to Strood to set out the helical flight. The others lads are in central London, 2 new jobs starting.
This blog is a brief insight into the day to day dealings of an in situ concrete staircase company
Monday, 31 July 2017
Sunday, 30 July 2017
Dreaded Monday Blog
2 lads off to Birmingham to form/cast closed string on the stairs we cast last week. Mattie striking the stairs in Rugby and Kevin in the lorry. BUSY BUSY Monday
Concrete Stairs Blog
Down to yard this morning to load the lorry for tomorrow. No peace for the wicked.
Concrete pour blog
2nd flight now poured in Northwood. A series of 3 straight flights, some with landings, basement-second floors.
Thursday, 27 July 2017
Concrete stairs Blog
We are starting a new job in Strood today. There are 2 concrete helical flights to complete. Will post pics at a later date.
Concrete stairs pour
We cast a stair in Birmingham today, standard helical, poured manually. The lads didnt mind as it was job and knock.
Wednesday, 26 July 2017