Thursday 8 November 2018

Exterior concrete stairs

A couple of recent projects we have completed. One a stepped soffit stair the other 2 standard straight flights. One flight did have rebates placed near the string edge for a glass balustrade.

Monday 29 October 2018

Concrete stairs

Concrete stairs poured today in Malmesbury.

The job at Edenhurst Ave almost ready for concrete. 

Thursday 25 October 2018

Back to work

First day back after my Ablation.

Been stressful, but life goes on.

Monday 22 October 2018

Early morning start

Heard we go again, another early start in the life of EJ Brennan.
Two lads off to Poole and 2 lads off to Birmingham.
I am still off after my heart procedure 2 weeks ago, back full time soon.

Concrete stairs

Sunday 21 October 2018

Saturday 20 October 2018

One happy Client!

Lovely when you get great feed back for your work!

Glowing report left by a Client in Ascot on a Facebook page.

Please see the image, great stuff.

Friday 19 October 2018

<a href='https://www.ejbformwork.co.uk/' title='concrete stairs' target='_blank'>concrete stairs</a>

Saturday 13 October 2018

Concrete stairs

Stairs cast in Barnet, crane winded off at palace, no concrete till next week.Concrete stairs

Sunday 7 October 2018

Concrete stairs

Concrete pour today in Maida Vale and the lads getting another pour ready in Palace street.

Concrete stairs

Concrete pour today in Maida Vale and the lads getting another pour ready in Palace street.

Concrete stairs on a Sunday

It would be lovely to have a day off, but running a Concrete Stairs business means being busy all the time.
In between, emails, pricing works and invoicing, I might get a chance to have a Sunday roast.


concrete stairs

Thursday 4 October 2018

Spiral concrete stairs

Biggest gripe with running your own company, getting paid!!!

A client is great with communication when they want the work done.

Unfortunately, it seems more and more become incommunicado when payment is due.

Wednesday 3 October 2018

Finished concrete stairs

Always great when you return back to site and get a picture of your stairs.

The solid concrete balustrade finished with a smooth render.

.

Tuesday 2 October 2018

Concrete Stairs

Final concrete stairs being poured today in Cheltenham.

Formwork being removed in Taunton.

Chippies continuing in Palace street London. 

EJ Brennan

Monday 1 October 2018

Sunday 30 September 2018

Saturday 29 September 2018

Website

A hectic and stressful week sorting out my website. I finally think it's sorted.

Many thanks Monitor backlinks!

Thursday 27 September 2018

Concrete stairs in London

Working in London is great and we have completed hundreds of concrete stairs up there.
These range from new builds, but the majority are in re-furbs.

Wednesday 26 September 2018

Back links scam

Unfortunately, we live in a dishonest, achieve anything at any cost society.If someone has success, others want a piece of it and will do anything to achieve this. My website has had numerous, spam back links pointed at it, thus resulting in a slight fall in my Google page ranking.

The scam involves taking images from my site and placing them on spam websites. These websites have hundreds of spam links attached to them.

Well, I have attacked back, thank God for the monitor backlinks team. I have successfully disavowed this links and my website is in recovery mode.

Concrete stairs in London

We are returning to Palace street next week to continue with the works on the Carey/Scudder project.

Six more flights to go out of 13.

https://www.careysplc.co.uk/scudder-demolition

#ejbrennanformworkltd 

Tuesday 25 September 2018

Concrete stairs

Reinforcement completed on Byfleet stairs and the soffit cut in on the 3rd flight in Cheltenham.

Concrete stairs in Byfleet

Steel reinforcement being tied on our project in Byfleet.

https://www.ejbformwork.co.uk/

Stepped soffit stairs on a recent project


Thursday 20 September 2018

Thursday 13 September 2018

Concrete stairs

New job started today near Croydon for the Contractor- Cobalt Green. Two sets of external stairs.

Sunday 9 September 2018

Concrete stairs

Formwork finished at Crystal Palace and concrete ordered for Weds morning.

Thursday 6 September 2018

Concrete stairs

Reinforcement completed on Palace park job, looking to pour early next week.

Tuesday 4 September 2018

Concrete stairs

New job opposite Stockwell tube station. The access is awful😩😩😩😩

Thursday 30 August 2018

Concrete stairs

Almost ready for concrete in Canon hill and Cheltenham job well advanced.

Sunday 26 August 2018

Beautifully finished staircase on a project in South Wales.


https://www.ejbformwork.co.uk/

Friday 24 August 2018

Concrete pour

Steps being poured at four seasons Hopk and stairs cast at Palace street.

Thursday 23 August 2018

Concrete stairs

Purley ready for concrete, also Palace street. Striking first flight in Cheltenham.

Friday 17 August 2018

Friday 10 August 2018

Tuesday 7 August 2018

Saturday 4 August 2018

Tuesday 31 July 2018

Concrete stairs

Stairs struck in Palace street, stair Formwork finished in Cheltenham.

Sunday 29 July 2018

Thursday 26 July 2018

Concrete stairs

Site meeting in West London, 4 flights - stepped soffit concrete stairs.

Wednesday 25 July 2018

Concrete stairs

Flight 4 in Palace street ready and flight number 2 in Beaconsfield almost done.

Monday 23 July 2018

Concrete stairs in Worcester

Disaster today, new job for Aasia, Centenary lounge coffee shop in Worcester.

The steels in the wrong place, job aborted till remedied.😩😩😩

Wednesday 18 July 2018

Monday 16 July 2018

Concrete stairs

Setting out for second flight in Chigwell today, lads continuing in Palace Street.

Sunday 15 July 2018

Saturday 14 July 2018

Concrete stairs pour

Stairs poured today in Eastleach, had to mix by hand as Fairford air show caused chaos.

No concrete company would deliver due to traffic.

Another happy client though.

Friday 13 July 2018

In situ concrete stairs

First flight cast today in Palace street. Great compliment from J Carey himself today. Told us “we were the best in the business”

Thursday 12 July 2018

Stepped soffit concrete stairs 

New job in Eastleach, 1100 wide stepped soffit. House is a timber frame, but the Client insisted she wanted a concrete stairs after seeing our website.

Monday 9 July 2018

Concrete stairs with solid concrete balustrade.

Lovely concrete staircase with balustrades that we completed on a project in Little Chalfont. 

A tricky project due to the tight inner curve.



.

Friday 6 July 2018

Tuesday 3 July 2018

Concrete Stairs

New job started for Carey's at Palace Gate, SW London

A total of 13 Curved and Helical flights.

Saturday 23 June 2018

Large Helical Concrete Stairs

This "huge" Helical concrete staircase, landing areas/concrete balustrade.and support column was completed for JM Weston in Cheltenham.

Wednesday 20 June 2018

Thursday 24 May 2018

Monday 21 May 2018

Concrete pour

Lads getting the last few things ready for the big pour tomorrow in Cheltenham.

Thursday 17 May 2018

New job 

New job started today in London, straight flight, 1 metre wide, 19 risers.

Tuesday 8 May 2018

Concrete stairs

Drama today, had to cancel the pour, no pump 😩😩😩😩😩

Saturday 5 May 2018

Friday 4 May 2018

Polished concrete stairs

We completed this staircase on a project in Pangbourne. The stairs were polished after the Formwork was removed.

Tuesday 24 April 2018

Getting paid for your work

This is becoming an even more frustrating part of running your own company.
Thankfully, it is a small percentage who cause problems.
My advice is when working for larger Contractors, ensue that you have everything in writing.
If you don't, they will attempt to screw you over, i have learnt this.
Also ensure that you have an individual or company who can act on your behalf.




 Who wouldn't pay for this

Stepped soffit concrete stairs